Scope of Basic Engineering Design Package is to elaborate engineering documentation starting from a Process Design Package (PDP) produced by Licensor to better transfer the technology information to any EPC Contractor for Detail Engineering development and Construction.
- Reduce the overall schedule by about 4-6 months due to the overlapping activities with PDP;
- Profit generation
- Allow Licensee to involve a more competitive local EPC contractor without a specific experience
- Support to EPC contractor during project implementation
Typical BDEP main deliverables
- Process piping and instrumentation diagram (P&ID)
- Equipment and Instruments Process Data sheet
- Fire fighting and gas detectors layout (HSE)
- Underground, Preliminary foundation, architectural drawings for Building, one line steel structure
- Static equipment Mechanical Data Sheet for Purchase Requisition
- Heater exchanger Calculation
- 3D Model
- Control Room/rack room layout
- Machinery Mechanical Data sheet for Purchase requisition
- General Equipment Layout
- Critical lines studies
- Electrical one line diagram
- Electrical Network calculation
- Cable routing
- Electrical substation layout
- DCS/ESD specification
- Automation architecture
- Instrumentation data sheet for purchase